WA Queue Project TCS-02 — Wind in Adams, Washington

WA Queue Project TCS-02 — Wind in Adams, Washington is a 123.2 MW wind interconnection project in Adams, Washington with a current status of withdrawn. It is proposed to connect at Future Neilson Swithching Station.

123.2 MWCapacity
WithdrawnStatus
WAMarket
WindTechnology

Project facts

Canonical nameWA Queue Project TCS-02 — Wind in Adams, Washington
Queue IDTCS-02
Statuswithdrawn
Source statusWithdrawn
MarketWA
TechnologyWind
Capacity123.2 MW
StateWashington
CountyAdams
Point of interconnectionFuture Neilson Swithching Station
Requested (queue) date2018-06-08
Proposed in-service date2021-11-30
Operational date
Withdrawn date
Developer
Utility / transmission ownerAvista Utilities

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-28

Provenance: avista-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata