WA Queue Project TCS-10 — Solar+Battery in Lincoln, Washington

WA Queue Project TCS-10 — Solar+Battery in Lincoln, Washington is a 40.0 MW solar+battery interconnection project in Lincoln, Washington with a current status of withdrawn. It is proposed to connect at Harrington Substation 115kV.

40.0 MWCapacity
WithdrawnStatus
WAMarket
Solar+BatteryTechnology

Project facts

Canonical nameWA Queue Project TCS-10 — Solar+Battery in Lincoln, Washington
Queue IDTCS-10
Statuswithdrawn
Source statusWithdrawn
MarketWA
TechnologySolar+Battery
Capacity40.0 MW
StateWashington
CountyLincoln
Point of interconnectionHarrington Substation 115kV
Requested (queue) date2019-12-10
Proposed in-service date2021-07-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerAvista Utilities

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: avista-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata