Washita 138kV is a 74.2 MW wind interconnection project in Carnegie, Oklahoma with a current status of withdrawn. It is proposed to connect at Washita 138kV.

74.2 MWCapacity
WithdrawnStatus
OKMarket
WindTechnology

Project facts

Canonical nameWashita 138kV
Queue IDGEN-2023-GR6
Statuswithdrawn
Source statusWITHDRAWN
MarketOK
TechnologyWind
Capacity74.2 MW
StateOklahoma
CountyCarnegie
Point of interconnectionWashita 138kV
Requested (queue) date2023-07-14
Proposed in-service date2024-12-31
Operational date
Withdrawn date2024-08-30
Developer
Utility / transmission ownerWFEC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.