Washita 138kV Substation (ERAS-2025-025)

Washita 138kV Substation is a 175.0 MW solar interconnection project in Fort Cobb, Oklahoma with a current status of operational. It is proposed to connect at Washita 138kV Substation.

175.0 MWCapacity
OperationalStatus
OKMarket
SolarTechnology

Project facts

Canonical nameWashita 138kV Substation
Queue IDERAS-2025-025
Statusoperational
Source statusERAS
MarketOK
TechnologySolar
Capacity175.0 MW
StateOklahoma
CountyFort Cobb
Point of interconnectionWashita 138kV Substation
Requested (queue) date2025-10-02
Proposed in-service date
Operational date2027-05-01
Withdrawn date
Developer
Utility / transmission ownerWFEC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.