Waverly 345kV (GEN-2010-003)

Waverly 345kV is a 99.5 MW wind interconnection project in Coffey County, Kansas with a current status of operational. It is proposed to connect at Waverly 345kV.

99.5 MWCapacity
OperationalStatus
KSMarket
WindTechnology

Project facts

Canonical nameWaverly 345kV
Queue IDGEN-2010-003
Statusoperational
Source statusIA FULLY EXECUTED/COMMERCIAL OPERATION
MarketKS
TechnologyWind
Capacity99.5 MW
StateKansas
CountyCoffey County
Point of interconnectionWaverly 345kV
Requested (queue) date2010-03-08
Proposed in-service date
Operational date2011-12-31
Withdrawn date
Developer
Utility / transmission ownerWERE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata