Wein - Stratford 115 kV Line Tap (J821)

Wein - Stratford 115 kV Line Tap is a 99.9 MW wind interconnection project in Marathon County, Wisconsin with a current status of withdrawn. It is proposed to connect at Wein - Stratford 115 kV Line Tap.

99.9 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameWein - Stratford 115 kV Line Tap
Queue IDJ821
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity99.9 MW
StateWisconsin
CountyMarathon County
Point of interconnectionWein - Stratford 115 kV Line Tap
Requested (queue) date2017-06-16
Proposed in-service date2020-09-15
Operational date2020-09-15
Withdrawn date2020-05-26
Developer
Utility / transmission ownerAMERICAN TRANSMISSION COMPANY

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.