West Queue Project 12-051 — Gas in Cowlitz, Washington

West Queue Project 12-051 — Gas in Cowlitz, Washington is a 375.0 MW gas interconnection project in Cowlitz, Washington with a current status of suspended. It is proposed to connect at Trojan Substation @ 230 kV.

375.0 MWCapacity
SuspendedStatus
WestMarket
GasTechnology

Project facts

Canonical nameWest Queue Project 12-051 — Gas in Cowlitz, Washington
Queue ID12-051
Statussuspended
Source statussuspended
MarketWest
TechnologyGas
Capacity375.0 MW
StateWashington
CountyCowlitz
Point of interconnectionTrojan Substation @ 230 kV
Requested (queue) date2012-07-16
Proposed in-service date2016-11-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerPortland General Electric

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata