West Queue Project 191 — Wind in Carbon, Wyoming

West Queue Project 191 — Wind in Carbon, Wyoming is a 500.0 MW wind interconnection project in Carbon, Wyoming with a current status of withdrawn. It is proposed to connect at Jim Bridger - Aeolus.

500.0 MWCapacity
WithdrawnStatus
WestMarket
WindTechnology

Project facts

Canonical nameWest Queue Project 191 — Wind in Carbon, Wyoming
Queue ID191
Statuswithdrawn
Source statuswithdrawn
MarketWest
TechnologyWind
Capacity500.0 MW
StateWyoming
CountyCarbon
Point of interconnectionJim Bridger - Aeolus
Requested (queue) date2008-01-25
Proposed in-service date
Operational date
Withdrawn date2015-07-13
Developer
Utility / transmission ownerPacifiCorp

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata