West Queue Project 243 — Wind in Bonneville, Idaho is a 64.8 MW wind interconnection project in Bonneville, Idaho with a current status of withdrawn. It is proposed to connect at Line to existing Wolverine Creek Goshen substation phase II.

64.8 MWCapacity
WithdrawnStatus
WestMarket
WindTechnology

Project facts

Canonical nameWest Queue Project 243 — Wind in Bonneville, Idaho
Queue ID243
Statuswithdrawn
Source statuswithdrawn
MarketWest
TechnologyWind
Capacity64.8 MW
StateIdaho
CountyBonneville
Point of interconnectionLine to existing Wolverine Creek Goshen substation phase II
Requested (queue) date2008-11-06
Proposed in-service date2009-11-01
Operational date
Withdrawn date
DeveloperRidgeline Energy, LLC
Utility / transmission ownerPacifiCorp

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.