West Point II HVDC (0615)
West Point II HVDC is a 1,000.0 MW other interconnection project in Albany-Westchester, New York with a current status of withdrawn. It is proposed to connect at New Scotland - Buchanan South 345kV.
1,000.0 MWCapacity
WithdrawnStatus
F, HMarket
OtherTechnology
Project facts
| Canonical name | West Point II HVDC |
|---|---|
| Queue ID | 0615 |
| Status | withdrawn |
| Source status | 0 |
| Market | F, H |
| Technology | Other |
| Capacity | 1,000.0 MW |
| State | New York |
| County | Albany-Westchester |
| Point of interconnection | New Scotland - Buchanan South 345kV |
| Requested (queue) date | 2017-03-02 |
| Proposed in-service date | 2019-02-28 |
| Operational date | — |
| Withdrawn date | — |
| Developer | West Point Partners, LLC |
| Utility / transmission owner | NM-NG |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata