West Queue Project Q231 — Solar in Cochise, Arizona

West Queue Project Q231 — Solar in Cochise, Arizona is a 17.5 MW solar interconnection project in Cochise, Arizona with a current status of withdrawn. It is proposed to connect at Fairview Substation.

17.5 MWCapacity
WithdrawnStatus
WestMarket
SolarTechnology

Project facts

Canonical nameWest Queue Project Q231 — Solar in Cochise, Arizona
Queue IDQ231
Statuswithdrawn
Source statuswithdrawn
MarketWest
TechnologySolar
Capacity17.5 MW
StateArizona
CountyCochise
Point of interconnectionFairview Substation
Requested (queue) date2015-10-09
Proposed in-service date2016-12-15
Operational date
Withdrawn date
Developer
Utility / transmission ownerArizona Public Service

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata