West Queue Project Q366 — Wind in Coconino, Arizona
West Queue Project Q366 — Wind in Coconino, Arizona is a 400.0 MW wind interconnection project in Coconino, Arizona with a current status of withdrawn. It is proposed to connect at Cholla-Pinnacle Peak 345kV or APS‚Äôs Cholla - Preacher Canyon 345kV..
Project facts
| Canonical name | West Queue Project Q366 — Wind in Coconino, Arizona |
|---|---|
| Queue ID | Q366 |
| Status | withdrawn |
| Source status | withdrawn |
| Market | West |
| Technology | Wind |
| Capacity | 400.0 MW |
| State | Arizona |
| County | Coconino |
| Point of interconnection | Cholla-Pinnacle Peak 345kV or APS’s Cholla - Preacher Canyon 345kV. |
| Requested (queue) date | 2021-01-14 |
| Proposed in-service date | 2024-12-01 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Arizona Public Service |
What changed
No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.
Explore related data
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata