West Queue Project Q6 — Wind in Navajo, Arizona
West Queue Project Q6 — Wind in Navajo, Arizona is a 65.1 MW wind interconnection project in Navajo, Arizona with a current status of operational. It is proposed to connect at Cholla/ Zeniff/ Show Low Western 69kV line and Cholla / Show Low Eastern 69kV line.
Project facts
| Canonical name | West Queue Project Q6 — Wind in Navajo, Arizona |
|---|---|
| Queue ID | Q6 |
| Status | operational |
| Source status | operational |
| Market | West |
| Technology | Wind |
| Capacity | 65.1 MW |
| State | Arizona |
| County | Navajo |
| Point of interconnection | Cholla/ Zeniff/ Show Low Western 69kV line and Cholla / Show Low Eastern 69kV line |
| Requested (queue) date | 2005-04-29 |
| Proposed in-service date | 2011-01-15 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Arizona Public Service |
What changed
No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.
Explore related data
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata