White Oak is a 4.5 MW gas interconnection project in Montgomery, Maryland with a current status of operational.

4.5 MWCapacity
OperationalStatus
Market
GasTechnology

Project facts

Canonical nameWhite Oak
Queue IDV2-037
Statusoperational
Source statusIn Service
Market
TechnologyGas
Capacity4.5 MW
StateMaryland
CountyMontgomery
Point of interconnection
Requested (queue) date2009-07-24
Proposed in-service date
Operational date2010-05-03
Withdrawn date
Developer
Utility / transmission ownerPEPCO

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.