Whitten 115kV (GEN-2014-065)

Whitten 115kV is a 99.0 MW solar interconnection project in Lea, New Mexico with a current status of withdrawn. It is proposed to connect at Whitten 115kV.

99.0 MWCapacity
WithdrawnStatus
NMMarket
SolarTechnology

Project facts

Canonical nameWhitten 115kV
Queue IDGEN-2014-065
Statuswithdrawn
Source statusWITHDRAWN
MarketNM
TechnologySolar
Capacity99.0 MW
StateNew Mexico
CountyLea
Point of interconnectionWhitten 115kV
Requested (queue) date2014-09-30
Proposed in-service date
Operational date
Withdrawn date2015-10-22
Developer
Utility / transmission ownerSPS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.