Wichita 345 (GEN-2013-044)
Wichita 345 is a 136.0 MW wind interconnection project in Sumner, Kansas with a current status of withdrawn. It is proposed to connect at Wichita 345.
136.0 MWCapacity
WithdrawnStatus
KSMarket
WindTechnology
Project facts
| Canonical name | Wichita 345 |
|---|---|
| Queue ID | GEN-2013-044 |
| Status | withdrawn |
| Source status | WITHDRAWN |
| Market | KS |
| Technology | Wind |
| Capacity | 136.0 MW |
| State | Kansas |
| County | Sumner |
| Point of interconnection | Wichita 345 |
| Requested (queue) date | 2013-12-20 |
| Proposed in-service date | — |
| Operational date | — |
| Withdrawn date | 2014-02-11 |
| Developer | — |
| Utility / transmission owner | WERE |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata