Wind (382)
Wind is a 79.9 MW wind interconnection project in Oxford, Maine with a current status of withdrawn. It is proposed to connect at CMP 115 kV Rumford to Livermore Line.
79.9 MWCapacity
WithdrawnStatus
MEMarket
WindTechnology
Project facts
| Canonical name | Wind |
|---|---|
| Queue ID | 382 |
| Status | withdrawn |
| Source status | W |
| Market | ME |
| Technology | Wind |
| Capacity | 79.9 MW |
| State | Maine |
| County | Oxford |
| Point of interconnection | CMP 115 kV Rumford to Livermore Line |
| Requested (queue) date | 2011-12-05 |
| Proposed in-service date | 2014-10-31 |
| Operational date | — |
| Withdrawn date | 2012-11-20 |
| Developer | — |
| Utility / transmission owner | ISO-NE |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27
Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.