wind (532)

wind is a 17.4 MW wind interconnection project in Franklin, Vermont with a current status of withdrawn. It is proposed to connect at GMP 34.5 kV Line between North St. Albans and Sheldon Springs Substations. State Route 105, Swanton, Vermont.

17.4 MWCapacity
WithdrawnStatus
VTMarket
WindTechnology

Project facts

Canonical namewind
Queue ID532
Statuswithdrawn
Source statusW
MarketVT
TechnologyWind
Capacity17.4 MW
StateVermont
CountyFranklin
Point of interconnectionGMP 34.5 kV Line between North St. Albans and Sheldon Springs Substations. State Route 105, Swanton, Vermont
Requested (queue) date2015-02-27
Proposed in-service date2016-09-15
Operational date
Withdrawn date2016-06-01
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.