Wind (536)
Wind is a 5.0 MW wind interconnection project in Orleans, Vermont with a current status of withdrawn. It is proposed to connect at GMP Line 14 between Irasburg and Lowell Substations approximately 3.6 miles from Irasburg Substation adjacent to Kidder Hill Road.
5.0 MWCapacity
WithdrawnStatus
VTMarket
WindTechnology
Project facts
| Canonical name | Wind |
|---|---|
| Queue ID | 536 |
| Status | withdrawn |
| Source status | W |
| Market | VT |
| Technology | Wind |
| Capacity | 5.0 MW |
| State | Vermont |
| County | Orleans |
| Point of interconnection | GMP Line 14 between Irasburg and Lowell Substations approximately 3.6 miles from Irasburg Substation adjacent to Kidder Hill Road |
| Requested (queue) date | 2015-02-27 |
| Proposed in-service date | 2016-09-13 |
| Operational date | — |
| Withdrawn date | 2015-12-10 |
| Developer | — |
| Utility / transmission owner | ISO-NE |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27
Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata