Wind project point-to-point application is a 100.0 MW generation interconnection project in Aroostoock, Maine with a current status of withdrawn.
100.0 MWCapacity
WithdrawnStatus
BHEMarket
GenerationTechnology
Project facts
| Canonical name | Wind project point-to-point application |
|---|---|
| Queue ID | 274 |
| Status | withdrawn |
| Source status | W |
| Market | BHE |
| Technology | Generation |
| Capacity | 100.0 MW |
| State | Maine |
| County | Aroostoock |
| Point of interconnection | — |
| Requested (queue) date | 2008-08-25 |
| Proposed in-service date | 2011-10-01 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | ISO-NE |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27
Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.