Windy Ridge Wind Farm (G85)

Windy Ridge Wind Farm is a 150.0 MW wind interconnection project in Garfield, Washington with a current status of withdrawn. It is proposed to connect at BPA's Lower Monumental Substation.

150.0 MWCapacity
WithdrawnStatus
WAMarket
WindTechnology

Project facts

Canonical nameWindy Ridge Wind Farm
Queue IDG85
Statuswithdrawn
Source statusWITHDRAWN
MarketWA
TechnologyWind
Capacity150.0 MW
StateWashington
CountyGarfield
Point of interconnectionBPA's Lower Monumental Substation
Requested (queue) date2001-10-29
Proposed in-service date2004-01-01
Operational date
Withdrawn date
DeveloperWinds Over Washington Energy Group
Utility / transmission ownerBonneville Power Administration

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.