WMA300SB (Q25-LG-5-13)

WMA300SB is a 250.0 MW solar+battery interconnection project in Sierra County, New Mexico with a current status of active. It is proposed to connect at West Mesa-Arroyo 345 kV Line.

250.0 MWCapacity
ActiveStatus
NMMarket
Solar+BatteryTechnology

Project facts

Canonical nameWMA300SB
Queue IDQ25-LG-5-13
Statusactive
Source status—
MarketNM
TechnologySolar+Battery
Capacity250.0 MW
StateNew Mexico
CountySierra County
Point of interconnectionWest Mesa-Arroyo 345 kV Line
Requested (queue) date2025-05-13
Proposed in-service date2029-12-31
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerEl Paso Electric Company

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-11-09phaseN/ACluster Studylow
2026-11-09proposed_online_date2029-06-012029-12-31medium
2026-08-03new_project—activehigh

Explore related data

Source last checked2026-11-23
Data last materially changed2026-11-23
Page data generated2026-11-26

Provenance: epe-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata