Woodring 345kV Substation (GEN-2024-SR11)

Woodring 345kV Substation is a 200.0 MW battery interconnection project in Garfield, Oklahoma with a current status of operational. It is proposed to connect at Woodring 345kV Substation.

200.0 MWCapacity
OperationalStatus
OKMarket
BatteryTechnology

Project facts

Canonical nameWoodring 345kV Substation
Queue IDGEN-2024-SR11
Statusoperational
Source statusIA FULLY EXECUTED/COMMERCIAL OPERATION
MarketOK
TechnologyBattery
Capacity200.0 MW
StateOklahoma
CountyGarfield
Point of interconnectionWoodring 345kV Substation
Requested (queue) date2024-05-07
Proposed in-service date—
Operational date2025-12-02
Withdrawn date—
Developer—
Utility / transmission ownerOGE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-09operational_date—2025-12-02medium
2026-09-09proposed_online_date2025-12-02—medium
2026-09-09statusactiveoperationalhigh
2026-07-31new_project—activehigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.