Woodward EHV 138kV (GEN-2008-029)

Woodward EHV 138kV is a 250.5 MW wind interconnection project in Ellis County, Oklahoma with a current status of withdrawn. It is proposed to connect at Woodward EHV 138kV.

250.5 MWCapacity
WithdrawnStatus
OKMarket
WindTechnology

Project facts

Canonical nameWoodward EHV 138kV
Queue IDGEN-2008-029
Statuswithdrawn
Source statusWITHDRAWN
MarketOK
TechnologyWind
Capacity250.5 MW
StateOklahoma
CountyEllis County
Point of interconnectionWoodward EHV 138kV
Requested (queue) date2008-04-17
Proposed in-service date
Operational date
Withdrawn date2011-04-12
Developer
Utility / transmission ownerOGE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata