Worden Substation (L0338)

Worden Substation is a 100.0 MW other interconnection project in Franklin, Washington with a current status of operational. It is proposed to connect at BPA's Franklin-Walla Walla 115kV Line 13/6.

100.0 MWCapacity
OperationalStatus
WAMarket
OtherTechnology

Project facts

Canonical nameWorden Substation
Queue IDL0338
Statusoperational
Source statusENERGIZED
MarketWA
TechnologyOther
Capacity100.0 MW
StateWashington
CountyFranklin
Point of interconnectionBPA's Franklin-Walla Walla 115kV Line 13/6
Requested (queue) date2011-10-26
Proposed in-service date
Operational date2013-01-01
Withdrawn date
DeveloperColumbia Rural Electric Association
Utility / transmission ownerBonneville Power Administration

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata