WY Queue Project 2009-G2 — Wind in Laramie County, Wyoming

WY Queue Project 2009-G2 — Wind in Laramie County, Wyoming is a 200.0 MW wind interconnection project in Laramie County, Wyoming with a current status of withdrawn. It is proposed to connect at Cheyenne-Miracle Mile.

200.0 MWCapacity
WithdrawnStatus
WYMarket
WindTechnology

Project facts

Canonical nameWY Queue Project 2009-G2 — Wind in Laramie County, Wyoming
Queue ID2009-G2
Statuswithdrawn
Source statusRemoved from Queue
MarketWY
TechnologyWind
Capacity200.0 MW
StateWyoming
CountyLaramie County
Point of interconnectionCheyenne-Miracle Mile
Requested (queue) date2009-03-17
Proposed in-service date2011-07-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerWestern Area Power Administration - Rocky Mountain Region

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: wapa-rm-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.