WY Queue Project 2025-G5 — Solar in Natrona County, Wyoming
WY Queue Project 2025-G5 — Solar in Natrona County, Wyoming is a 100.0 MW solar interconnection project in Natrona County, Wyoming with a current status of active. It is proposed to connect at Bucknum Tap Substation 115kV.
100.0 MWCapacity
ActiveStatus
WYMarket
SolarTechnology
Project facts
| Canonical name | WY Queue Project 2025-G5 — Solar in Natrona County, Wyoming |
|---|---|
| Queue ID | 2025-G5 |
| Status | active |
| Source status | In Progress |
| Market | WY |
| Technology | Solar |
| Capacity | 100.0 MW |
| State | Wyoming |
| County | Natrona County |
| Point of interconnection | Bucknum Tap Substation 115kV |
| Requested (queue) date | 2025-09-30 |
| Proposed in-service date | 2028-07-30 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Western Area Power Administration - Rocky Mountain Region |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-03 | new_project | — | active | high |
Explore related data
Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27
Provenance: wapa-rm-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata