WY Queue Project PIS004 — Wind in Carbon, Wyoming

WY Queue Project PIS004 — Wind in Carbon, Wyoming is a 500.0 MW wind interconnection project in Carbon, Wyoming with a current status of withdrawn. It is proposed to connect at Aeolus substation.

500.0 MWCapacity
WithdrawnStatus
WYMarket
WindTechnology

Project facts

Canonical nameWY Queue Project PIS004 — Wind in Carbon, Wyoming
Queue IDPIS004
Statuswithdrawn
Source statusWithdrawn
MarketWY
TechnologyWind
Capacity500.0 MW
StateWyoming
CountyCarbon
Point of interconnectionAeolus substation
Requested (queue) date2022-04-20
Proposed in-service date2025-01-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerPacifiCorp

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: pacificorp-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.