Leflore County, Mississippi — Interconnection Projects

The interXdata warehouse tracks 5 interconnection projects in Leflore, Mississippi, representing 700 MW of requested capacity.

5Total projects
0Active
1Operational
4Withdrawn
700 MWRequested capacity

Technology mix

TechnologyProjectsRequested capacity
Solar4650 MW
Battery150 MW

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
SCHLATERJ3568Solar250.0 MWwithdrawnLeflore, Mississippi
GREENWOODJ2330Solar200.0 MWoperationalLeflore, Mississippi
Itta Benna - Moorhead 115KVJ2162Solar100.0 MWwithdrawnLeflore, Mississippi
Greenwood - Pickens 115 kVJ1509Solar100.0 MWwithdrawnLeflore, Mississippi
Greenwood - Pickens 115 kVJ1523Battery50.0 MWwithdrawnLeflore, Mississippi

Top developers

Developer attribution is not yet resolved for this set.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.