Perry County, Missouri — Interconnection Projects
The interXdata warehouse tracks 3 interconnection projects in Perry, Missouri, representing 282 MW of requested capacity.
3Total projects
0Active
0Operational
3Withdrawn
282 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 2 | 250 MW |
| Other | 1 | 32 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Seminary/Perryville 138kV | J1764 | Solar | 125.0 MW | withdrawn | Perry, Missouri |
| MISO Queue Project J1764 — Solar in Perry, Missouri | J1764 | Solar | 125.0 MW | withdrawn | Perry, Missouri |
| MISO Queue Project J047 — Other in Perry, Missouri | J047 | Other | 32.5 MW | withdrawn | Perry, Missouri |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-01
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; miso-giqueue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Perry County.