Atoka County, Oklahoma — Interconnection Projects
The interXdata warehouse tracks 5 interconnection projects in Atoka, Oklahoma, representing 722 MW of requested capacity.
5Total projects
1Active
0Operational
4Withdrawn
722 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 4 | 523 MW |
| Battery | 1 | 199 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Pittsburg - Valliant 345 kV Line | GEN-2024-316 | Solar | 300.0 MW | withdrawn | Atoka, Oklahoma |
| Atoka to Lehigh 138 kV Line | GEN-2024-184 | Battery | 199.0 MW | withdrawn | Atoka, Oklahoma |
| Tupelo - Atoka 138 kV Line | GEN-2023-069 | Solar | 100.0 MW | active | Atoka, Oklahoma |
| 138kV Atoka substation | GEN-2019-015 | Solar | 72.6 MW | withdrawn | Atoka, Oklahoma |
| Lane - McGee Creek Tap 69 kV | GEN-2023-070 | Solar | 50.0 MW | withdrawn | Atoka, Oklahoma |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Atoka County.