Creek County, Oklahoma — Interconnection Projects
The interXdata warehouse tracks 3 interconnection projects in Creek, Oklahoma, representing 1,640 MW of requested capacity.
3Total projects
1Active
1Operational
1Withdrawn
1,640 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Gas | 1 | 1,400 MW |
| Battery | 2 | 240 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Riverside – Redbud 345 kV line | GEN-2024-340 | Gas | 1,400.0 MW | operational | Creek, Oklahoma |
| Silver City 138 kV Substation | GEN-2024-169 | Battery | 140.0 MW | withdrawn | Creek, Oklahoma |
| Silver City 138 kV Substation | GEN-2022-156 | Battery | 100.0 MW | active | Creek, Oklahoma |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.