City of Burlington Electric - (VT) — Interconnection Queue Projects

City of Burlington Electric - (VT) is associated with 9 tracked interconnection projects representing 103 MW of requested capacity.

Entity resolution: this utility / transmission entity rolls up 4 source organization name(s) that were auto-matched into a single canonical cluster. Attribution is inferred from source records and may include related special-purpose entities.

9Projects
0Active
9Operational
0Withdrawn
103 MWRequested capacity
0Markets

Capacity by technology

TechnologyProjectsRequested capacity
Other898 MW
Gas15 MW

Geographic footprint

StateProjects
Vermont5
Kansas4

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
J C McNeil589_1Other59.5 MWoperationalChittenden, Vermont
Burlington GT3754_GT1Other25.5 MWoperationalChittenden, Vermont
Burlington (KS)1266_IC6Gas4.8 MWoperationalCoffey, Kansas
Chace Mill Winooski One54355_GEN1Other2.5 MWoperationalChittenden, Vermont
Chace Mill Winooski One54355_GEN3Other2.5 MWoperationalChittenden, Vermont
Chace Mill Winooski One54355_GEN2Other2.5 MWoperationalChittenden, Vermont
Burlington (KS)1266_4AOther2.3 MWoperationalCoffey, Kansas
Burlington (KS)1266_1AOther2.0 MWoperationalCoffey, Kansas
Burlington (KS)1266_2Other1.3 MWoperationalCoffey, Kansas

Recent material changes

No material field-level changes have been recorded against these projects since the baseline snapshot. interXdata records changes as new source snapshots are ingested and diffed.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Track queue activity connecting through City of Burlington Electric - (VT).

Start tracking with interXdata