CSU — Interconnection Queue Projects
CSU is associated with 2 tracked interconnection projects representing 238 MW of requested capacity.
Entity resolution: single source organization name; no cluster merge applied.
2Projects
0Active
2Operational
0Withdrawn
238 MWRequested capacity
0Markets
Capacity by technology
| Technology | Projects | Requested capacity |
|---|---|---|
| Gas | 1 | 178 MW |
| Solar | 1 | 60 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| West Queue Project CSU-2020-2 — Gas in an unlisted county, the U.S. | CSU-2020-2 | Gas | 178.0 MW | operational | — |
| West Queue Project CSU-2018-1 — Solar in an unlisted county, the U.S. | CSU-2018-1 | Solar | 60.0 MW | operational | — |
Recent material changes
No material field-level changes have been recorded against these projects since the baseline snapshot. interXdata records changes as new source snapshots are ingested and diffed.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.