Lansing Board of Water and Light — Interconnection Queue Projects

Lansing Board of Water and Light is associated with 7 tracked interconnection projects representing 361 MW of requested capacity.

Entity resolution: single source organization name; no cluster merge applied.

7Projects
0Active
7Operational
0Withdrawn
361 MWRequested capacity
1Markets

Capacity by technology

TechnologyProjectsRequested capacity
Gas7361 MW

Portfolio by market

MarketProjects
MISO7

Geographic footprint

StateProjects
Michigan7

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
Delta Energy Park63259_DEPSTGas89.2 MWoperationalEaton, Michigan
Delta Energy Park63259_DEPC2Gas58.0 MWoperationalEaton, Michigan
Delta Energy Park63259_DEPS1Gas58.0 MWoperationalEaton, Michigan
Delta Energy Park63259_DEPC3Gas58.0 MWoperationalEaton, Michigan
Lansing BWL REO Town Plant58427_CTG1Gas42.0 MWoperationalIngham, Michigan
Lansing BWL REO Town Plant58427_CTG2Gas42.0 MWoperationalIngham, Michigan
Lansing BWL REO Town Plant58427_STGas14.0 MWoperationalIngham, Michigan

Recent material changes

No material field-level changes have been recorded against these projects since the baseline snapshot. interXdata records changes as new source snapshots are ingested and diffed.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.