EmPower CES, LLC — Interconnection Portfolio
EmPower CES, LLC is associated with 737 tracked interconnection projects representing 130 MW of requested capacity.
Entity resolution: this developer rolls up 8 source organization name(s) that were auto-matched into a single canonical cluster. Attribution is inferred from source records and may include related special-purpose entities.
Capacity by technology
| Technology | Projects | Requested capacity |
|---|---|---|
| Gas | 1 | 123 MW |
| Battery | 395 | 4 MW |
| Solar | 341 | 4 MW |
Geographic footprint
| State | Projects |
|---|---|
| New York | 732 |
| California | 4 |
| Texas | 1 |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| EMPower Odessa (TEF - Due Diligence) | 27INR0272 | Gas | 122.8 MW | operational | Ector, Texas |
| PSEG Long Island DG PAM-2024-384645 | PAM-2024-384645 | Solar | 0.1 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2023-371983 | PAM-2023-371983 | Solar | 0.1 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2023-374508 | PAM-2023-374508 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2024-385060 | PAM-2024-385060 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island Storage PAM-2022-247388 | PAM-2022-247388 | Battery | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island Storage PAM-2021-141283 | PAM-2021-141283 | Battery | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island Storage PAM-2020-85150 | PAM-2020-85150 | Battery | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-392421 | PAM-2025-392421 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-389330 | PAM-2025-389330 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-389231 | PAM-2025-389231 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island Storage PAM-2024-379866 | PAM-2024-379866 | Battery | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-386987 | PAM-2025-386987 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-390571 | PAM-2025-390571 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-391509 | PAM-2025-391509 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-393467 | PAM-2025-393467 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-393462 | PAM-2025-393462 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-388804 | PAM-2025-388804 | Solar | 0.0 MW | operational | Nassau, New York |
| Con Edison DG SDG-80798 | SDG-80798 | Solar | 0.0 MW | operational | Westchester, New York |
| PSEG Long Island DG PAM-2025-392397 | PAM-2025-392397 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-391256 | PAM-2025-391256 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-392081 | PAM-2025-392081 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-387800 | PAM-2025-387800 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2024-384649 | PAM-2024-384649 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island Storage PAM-2024-384130 | PAM-2024-384130 | Battery | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island Storage PAM-2024-384078 | PAM-2024-384078 | Battery | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-386177 | PAM-2025-386177 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-393765 | PAM-2025-393765 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-393770 | PAM-2025-393770 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island Storage PAM-2024-383695 | PAM-2024-383695 | Battery | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-392357 | PAM-2025-392357 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island Storage PAM-2024-384094 | PAM-2024-384094 | Battery | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-389442 | PAM-2025-389442 | Solar | 0.0 MW | operational | Suffolk, New York |
| Con Edison DG SDG-90882 | SDG-90882 | Solar | 0.0 MW | operational | Westchester, New York |
| PSEG Long Island DG PAM-2025-392464 | PAM-2025-392464 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-387534 | PAM-2025-387534 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island Storage PAM-2021-150685 | PAM-2021-150685 | Battery | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island Storage PAM-2022-252874 | PAM-2022-252874 | Battery | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island Storage PAM-2022-281231 | PAM-2022-281231 | Battery | 0.0 MW | operational | Suffolk, New York |
| Con Edison Storage SDG-38612 | SDG-38612 | Battery | 0.0 MW | operational | Westchester, New York |
| PSEG Long Island Storage PAM-2024-384790 | PAM-2024-384790 | Battery | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2024-378313 | PAM-2024-378313 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2024-379392 | PAM-2024-379392 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-388036 | PAM-2025-388036 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-386482 | PAM-2025-386482 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-386989 | PAM-2025-386989 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-389431 | PAM-2025-389431 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-390663 | PAM-2025-390663 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-394428 | PAM-2025-394428 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-389237 | PAM-2025-389237 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-392013 | PAM-2025-392013 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-392522 | PAM-2025-392522 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-389950 | PAM-2025-389950 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-387611 | PAM-2025-387611 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-394149 | PAM-2025-394149 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-393902 | PAM-2025-393902 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-392017 | PAM-2025-392017 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-386975 | PAM-2025-386975 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-394232 | PAM-2025-394232 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-394620 | PAM-2025-394620 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-389196 | PAM-2025-389196 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-392739 | PAM-2025-392739 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-394661 | PAM-2025-394661 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-390581 | PAM-2025-390581 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-393863 | PAM-2025-393863 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-389592 | PAM-2025-389592 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-390515 | PAM-2025-390515 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-393051 | PAM-2025-393051 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-388020 | PAM-2025-388020 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-393525 | PAM-2025-393525 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-390756 | PAM-2025-390756 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-392000 | PAM-2025-392000 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-389593 | PAM-2025-389593 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-389989 | PAM-2025-389989 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-387629 | PAM-2025-387629 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-393469 | PAM-2025-393469 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-394638 | PAM-2025-394638 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-391998 | PAM-2025-391998 | Solar | 0.0 MW | operational | Suffolk, New York |
| PSEG Long Island DG PAM-2025-394470 | PAM-2025-394470 | Solar | 0.0 MW | operational | Nassau, New York |
| PSEG Long Island DG PAM-2025-394305 | PAM-2025-394305 | Solar | 0.0 MW | operational | Nassau, New York |
Recent material changes
No material field-level changes have been recorded against these projects since the baseline snapshot. interXdata records changes as new source snapshots are ingested and diffed.
Explore related data
Provenance: ca-dgstats; ERCOT — Generation Interconnection Status (GIS) report; ny-dg-solar; ny-storage. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Monitor EmPower CES, LLC's portfolio across all markets.
Start tracking with interXdata