12.47 kV line on #8110 circuit which is served from the Nashville Substation via transformers #2 and #3. (ASGI-2024-009)

12.47 kV line on #8110 circuit which is served from the Nashville Substation via transformers #2 and #3. is a 8.5 MW solar interconnection project in Nashville, Arkansas with a current status of operational. It is proposed to connect at 12.47 kV line on #8110 circuit which is served from the Nashville Substation via transformers #2 and #3..

8.5 MWCapacity
OperationalStatus
ARMarket
SolarTechnology

Project facts

Canonical name12.47 kV line on #8110 circuit which is served from the Nashville Substation via transformers #2 and #3.
Queue IDASGI-2024-009
Statusoperational
Source statusNone
MarketAR
TechnologySolar
Capacity8.5 MW
StateArkansas
CountyNashville
Point of interconnection12.47 kV line on #8110 circuit which is served from the Nashville Substation via transformers #2 and #3.
Requested (queue) date2025-03-12
Proposed in-service date
Operational date2025-09-01
Withdrawn date
Developer
Utility / transmission ownerAEP

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.