18-ALPHA BESS (28INR0328)

18-ALPHA BESS is a 307.4 MW other interconnection project in Cooke, Texas with a current status of operational. It is proposed to connect at To the 138 kV Valley View Substation, ( Bus No.691).

307.4 MWCapacity
OperationalStatus
CookeMarket
OtherTechnology

Project facts

Canonical name18-ALPHA BESS
Queue ID28INR0328
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketCooke
TechnologyOther
Capacity307.4 MW
StateTexas
CountyCooke
Point of interconnectionTo the 138 kV Valley View Substation, ( Bus No.691)
Requested (queue) date2025-04-21
Proposed in-service date
Operational date2028-02-01
Withdrawn date
DeveloperScout Energy Management, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.