Texas Interconnection Projects

interXdata tracks 6,817 interconnection projects in Texas representing 1,106,294 MW of requested capacity. The dominant technology by capacity is Solar. The most active counties are Harris, Brazoria, Carson.

6,817Total projects
872Active
4,693Operational
1,004Withdrawn
1,106,294 MWRequested capacity
161,474 MWActive capacity

Technology mix

TechnologyProjectsRequested capacity
Solar1,733355,481 MW
Other1,795276,642 MW
Gas1,793228,142 MW
Wind656134,868 MW
Battery77798,232 MW
Solar+Battery5111,412 MW
Wind+Battery5864 MW
Coal2465 MW
Oil3146 MW
Hydro127 MW
Nuclear113 MW

Counties

CountyProjectsRequested capacity
Harris41326,974 MW
Brazoria20828,452 MW
Carson17920,634 MW
Fort Bend15413,481 MW
Cameron15010,935 MW
Hidalgo14912,828 MW
Pecos13631,110 MW
Ector1199,735 MW
Wharton10823,142 MW
Bexar9811,591 MW
Bell889,006 MW
Galveston838,460 MW
Tarrant813,313 MW
Andrews766,515 MW
Nueces728,844 MW
Webb6811,552 MW
Hill6814,624 MW
Navarro6810,325 MW
Lamar6613,314 MW
Dallas664,679 MW
San Patricio6312,048 MW
Matagorda6313,042 MW
Travis632,855 MW
Reeves6211,086 MW
Scurry5811,458 MW
Milam5814,388 MW
Victoria577,405 MW
Ellis5310,206 MW
Starr539,076 MW
Upton5211,993 MW
Jefferson527,050 MW
Collin522,567 MW
Haskell5112,244 MW
Wilbarger5014,345 MW
Nolan499,204 MW
Frio493,952 MW
Borden4812,655 MW
Guadalupe467,606 MW
McLennan465,501 MW
Ward436,530 MW

Largest projects

ProjectQueue IDTechnologyCapacityStatusLocation
GEN-2008-031GEN-2008-031Wind4,000.0 MWwithdrawnWilbarger County, Texas
PC3000GQ26-LG-3-26-4Gas3,000.0 MWactiveEl Paso County, Texas
BM Great Rock Energy Center30INR0091Gas1,981.2 MWoperationalLeon, Texas
Prairie Ridge (Gas - CC)30INR0071Gas1,660.4 MWoperationalFranklin, Texas
Hecate Energy Orem Wind27INR0061Other1,542.0 MWoperationalBrazoria, Texas
Aegle Power27INR0084Gas1,536.4 MWoperationalCameron, Texas
Big Canyon Wind30INR0018Other1,500.0 MWoperationalPecos, Texas
Caldwell County Energy Center30INR0031Gas1,500.0 MWoperationalCaldwell, Texas
Liberty Thermal Energy Center33INR0006Gas1,400.0 MWoperationalHill, Texas
Bullock Gas33INR0005Gas1,400.0 MWoperationalHill, Texas
South Texas Project6251_2Other1,354.3 MWoperationalMatagorda, Texas
South Texas Project6251_1Other1,354.3 MWoperationalMatagorda, Texas
Willow Oak Gas30INR0020Gas1,350.0 MWoperationalJefferson, Texas
Pirkey 345 kV SubstationGEN-2024-377Gas1,350.0 MWoperationalHarrison, Texas
BasRanch (TEF - Due Diligence)25INR0008Gas1,350.0 MWoperationalWard, Texas
STP Unit2 High Pressure Turbine Upgrade27INR0557Other1,336.5 MWoperationalMatagorda, Texas
The Giant Arc-II30INR0105Gas1,300.0 MWoperationalPecos, Texas
The Giant Arc I30INR0113Gas1,300.0 MWoperationalPecos, Texas
Moon Hammer30INR0077Gas1,300.0 MWoperationalWheeler, Texas
Sandow Lakes Energy Station27INR0071Gas1,291.6 MWoperationalMilam, Texas
Aurelius 3 Natural Gas29INR0361Gas1,275.0 MWactiveDeaf Smith, Texas
Jewett Energy Center 1 Gas29INR0150Gas1,274.0 MWoperationalFreestone, Texas
Thunder Bird 2 Gas28INR0509Gas1,273.8 MWoperationalJack, Texas
Thunder Bird 1 Gas30INR0110Gas1,272.8 MWactiveJack, Texas
Mule Deer Run Gas II31INR0021Gas1,263.0 MWoperationalAnderson, Texas
Mule Deer Run Gas III31INR0022Gas1,263.0 MWoperationalAnderson, Texas
Mule Deer Run Gas32INR0003Gas1,263.0 MWoperationalAnderson, Texas
NRG Prairie Energy Center29INR0158Gas1,253.0 MWoperationalHill, Texas
Tolar Energy Center29INR0180Gas1,252.0 MWwithdrawnHood, Texas
Gravitas I Natural Gas30INR0084Gas1,247.0 MWoperationalPecos, Texas

Top developers in Texas

Recent material changes

ObservedProjectFieldOldNew
2026-10-06Plant X 115 kV Substationstatusactiveoperational
2026-10-06Plant X 115 kV Substationoperational_date—2026-04-01
2026-10-06Plant X 115 kV Substationproposed_online_date2026-04-01—
2026-10-03Tolk 230kV Substationoperational_date2028-10-31—
2026-10-03Tolk 230kV Substationproposed_online_date—2029-06-01
2026-10-03Tolk 230kV Substationstatusoperationalactive
2026-10-03Border-Tuco 345kV Lineoperational_date2030-06-14—
2026-10-03Border-Tuco 345kV Lineproposed_online_date—2030-10-01
2026-10-03Border-Tuco 345kV Linestatusoperationalactive
2026-10-03Mahoney 230kV Substationoperational_date2028-02-29—
2026-10-03Mahoney 230kV Substationproposed_online_date—2028-05-31
2026-10-03Mahoney 230kV Substationstatusoperationalactive

Explore related data

Source last checked2026-07-31
Data last materially changed2026-10-11
Page data generated2026-10-11

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); epe-oasis; ERCOT — Generation Interconnection Status (GIS) report; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; MISO — generator interconnection queue; Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.