Texas Interconnection Projects
interXdata tracks 6,848 interconnection projects in Texas representing 1,114,976 MW of requested capacity. The dominant technology by capacity is Solar. The most active counties are Harris, Brazoria, Carson.
6,848Total projects
873Active
4,686Operational
1,034Withdrawn
1,114,976 MWRequested capacity
160,617 MWActive capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 1,746 | 357,908 MW |
| Other | 1,783 | 276,283 MW |
| Gas | 1,799 | 231,809 MW |
| Wind | 657 | 135,163 MW |
| Battery | 800 | 100,885 MW |
| Solar+Battery | 51 | 11,412 MW |
| Wind+Battery | 5 | 864 MW |
| Coal | 2 | 465 MW |
| Oil | 3 | 146 MW |
| Hydro | 1 | 27 MW |
| Nuclear | 1 | 13 MW |
Counties
| County | Projects | Requested capacity |
|---|---|---|
| Harris | 414 | 26,984 MW |
| Brazoria | 210 | 28,589 MW |
| Carson | 179 | 20,634 MW |
| Fort Bend | 154 | 13,481 MW |
| Cameron | 150 | 10,935 MW |
| Hidalgo | 149 | 11,858 MW |
| Pecos | 137 | 31,273 MW |
| Ector | 119 | 9,735 MW |
| Wharton | 109 | 23,264 MW |
| Bexar | 98 | 11,591 MW |
| Bell | 88 | 9,006 MW |
| Galveston | 83 | 8,460 MW |
| Tarrant | 81 | 3,313 MW |
| Andrews | 76 | 6,515 MW |
| Nueces | 73 | 8,894 MW |
| Hill | 68 | 14,624 MW |
| Webb | 68 | 11,552 MW |
| Navarro | 68 | 10,525 MW |
| Lamar | 66 | 13,314 MW |
| Dallas | 66 | 4,679 MW |
| Matagorda | 64 | 13,182 MW |
| Travis | 63 | 2,855 MW |
| Reeves | 63 | 12,338 MW |
| San Patricio | 63 | 12,049 MW |
| Victoria | 59 | 8,726 MW |
| Milam | 59 | 14,599 MW |
| Scurry | 58 | 11,455 MW |
| Starr | 54 | 9,323 MW |
| Ellis | 54 | 10,226 MW |
| Collin | 52 | 2,567 MW |
| Upton | 52 | 11,956 MW |
| Jefferson | 52 | 6,998 MW |
| Haskell | 51 | 12,244 MW |
| Wilbarger | 50 | 14,345 MW |
| Frio | 49 | 3,952 MW |
| Nolan | 49 | 9,204 MW |
| Borden | 48 | 12,655 MW |
| Guadalupe | 47 | 7,616 MW |
| McLennan | 46 | 5,501 MW |
| Ward | 43 | 6,530 MW |
Largest projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| GEN-2008-031 | GEN-2008-031 | Wind | 4,000.0 MW | withdrawn | Wilbarger County, Texas |
| PC3000G | Q26-LG-3-26-4 | Gas | 3,000.0 MW | active | El Paso County, Texas |
| Brazos Energy Security | 28INR0456 | Gas | 3,000.0 MW | operational | Fisher, Texas |
| BM Great Rock Energy Center | 30INR0091 | Gas | 1,981.2 MW | operational | Leon, Texas |
| Prairie Ridge (Gas - CC) | 30INR0071 | Gas | 1,660.4 MW | operational | Franklin, Texas |
| Hecate Energy Orem Wind | 27INR0061 | Other | 1,542.0 MW | operational | Brazoria, Texas |
| Aegle Power | 27INR0084 | Gas | 1,536.4 MW | operational | Cameron, Texas |
| Big Canyon Wind | 30INR0018 | Other | 1,500.0 MW | operational | Pecos, Texas |
| Caldwell County Energy Center | 30INR0031 | Gas | 1,500.0 MW | operational | Caldwell, Texas |
| Bullock Gas | 33INR0005 | Gas | 1,400.0 MW | operational | Hill, Texas |
| Liberty Thermal Energy Center | 33INR0006 | Gas | 1,400.0 MW | operational | Hill, Texas |
| South Texas Project | 6251_2 | Other | 1,354.3 MW | operational | Matagorda, Texas |
| South Texas Project | 6251_1 | Other | 1,354.3 MW | operational | Matagorda, Texas |
| Pirkey 345 kV Substation | GEN-2024-377 | Gas | 1,350.0 MW | operational | Harrison, Texas |
| BasRanch (TEF - Due Diligence) | 25INR0008 | Gas | 1,350.0 MW | operational | Ward, Texas |
| STP Unit2 High Pressure Turbine Upgrade | 27INR0557 | Other | 1,336.5 MW | operational | Matagorda, Texas |
| Blue Energy Center - Phase 3 – Steam Stage 2 | 33INR0007 | Other | 1,320.0 MW | active | Victoria, Texas |
| Moon Hammer | 30INR0077 | Gas | 1,300.0 MW | operational | Wheeler, Texas |
| The Giant Arc I | 30INR0113 | Gas | 1,300.0 MW | operational | Pecos, Texas |
| The Giant Arc-II | 30INR0105 | Gas | 1,300.0 MW | operational | Pecos, Texas |
| Willow Oak Gas | 30INR0020 | Gas | 1,298.0 MW | operational | Jefferson, Texas |
| Sandow Lakes Energy Station | 27INR0071 | Gas | 1,291.6 MW | operational | Milam, Texas |
| Aurelius 3 Natural Gas | 29INR0361 | Gas | 1,275.0 MW | operational | Deaf Smith, Texas |
| Jewett Energy Center 1 Gas | 29INR0150 | Gas | 1,274.0 MW | operational | Freestone, Texas |
| Thunder Bird 1 Gas | 30INR0110 | Gas | 1,272.8 MW | active | Jack, Texas |
| Thunder Bird 2 Gas | 28INR0509 | Gas | 1,272.8 MW | operational | Jack, Texas |
| Mule Deer Run Gas | 32INR0003 | Gas | 1,263.0 MW | operational | Anderson, Texas |
| Mule Deer Run Gas III | 31INR0022 | Gas | 1,263.0 MW | operational | Anderson, Texas |
| Mule Deer Run Gas II | 31INR0021 | Gas | 1,263.0 MW | operational | Anderson, Texas |
| NRG Prairie Energy Center | 29INR0158 | Gas | 1,253.0 MW | operational | Hill, Texas |
Top developers in Texas
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Nextera | 40 | 9,741 MW |
| RWE Solar Development, LLC | 32 | 6,813 MW |
| Hecate Energy | 25 | 13,667 MW |
| Tempus Power management LLC | 24 | 3,056 MW |
| ABEI ENERGY&INFRASTRUCTURE LLC | 17 | 1,951 MW |
| HEN Infrastructure, LLC 1 | 16 | 159 MW |
| S&R SOLAR DESIGN CORP | 16 | 9,485 MW |
| ENGIE IR Holdings LLC | 15 | 3,802 MW |
| Innovative Solar 245, LLC | 15 | 1,240 MW |
| Invenergy | 14 | 3,975 MW |
| Cypress Creek Renewables | 13 | 1,618 MW |
| Eon | 13 | 2,919 MW |
| Black Mountain Energy Storage II | 12 | 4,170 MW |
| EDF Renewables Development, Inc. | 11 | 4,423 MW |
| BRP Blue Topaz 2, LLC | 10 | 1,901 MW |
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-11-25 | Kress 115 kV Substation | proposed_online_date | 2030-12-31 | 2031-05-01 |
| 2026-11-20 | Winnsboro 138 kV Substation | proposed_online_date | 2029-04-19 | 2029-10-15 |
| 2026-11-17 | Pirkey - Whitney 138 kV Line | proposed_online_date | 2028-03-31 | 2029-12-31 |
| 2026-11-17 | Hansford 115kV | withdrawn_date | — | 2026-10-30 |
| 2026-11-17 | Hansford 115kV | status | active | withdrawn |
| 2026-11-12 | TUCO-Oklaunion 345kV | proposed_online_date | 2026-10-15 | 2027-11-15 |
| 2026-11-09 | To199SB_2 | phase | N/A | Cluster Study, Facilities Study |
| 2026-11-09 | To199SB_1 | phase | N/A | Cluster Study, Facilities Study |
| 2026-11-09 | Ea150B | phase | N/A | Cluster Study, Facilities Study |
| 2026-11-09 | Sf150SB | proposed_online_date | 2027-05-01 | 2027-11-10 |
| 2026-11-05 | Cypress 138 kV Substation | withdrawn_date | — | 2026-10-20 |
| 2026-11-05 | Cypress 138 kV Substation | status | operational | withdrawn |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-11-26
Page data generated2026-11-26
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); epe-oasis; ERCOT — Generation Interconnection Status (GIS) report; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; MISO — generator interconnection queue; Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get notified when a new project appears in Texas.
Start tracking with interXdata