2 Cedar Wind (28INR0286)
2 Cedar Wind is a 180.0 MW other interconnection project in Fannin, Texas with a current status of operational. It is proposed to connect at Tap 345kV 1729 Valley South – Anna Switch 2373.
180.0 MWCapacity
OperationalStatus
FanninMarket
OtherTechnology
Project facts
| Canonical name | 2 Cedar Wind |
|---|---|
| Queue ID | 28INR0286 |
| Status | operational |
| Source status | SS Completed, FIS Started, No IA |
| Market | Fannin |
| Technology | Other |
| Capacity | 180.0 MW |
| State | Texas |
| County | Fannin |
| Point of interconnection | Tap 345kV 1729 Valley South – Anna Switch 2373 |
| Requested (queue) date | 2025-07-07 |
| Proposed in-service date | — |
| Operational date | 2028-05-02 |
| Withdrawn date | — |
| Developer | SunWR, LLC |
| Utility / transmission owner | ERCOT |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata