35 MW expansion of #757 is a 35.0 MW other interconnection project in Baker, Oregon with a current status of active. It is proposed to connect at OBSY 230kV Switchyard.

35.0 MWCapacity
ActiveStatus
ORMarket
OtherTechnology

Project facts

Canonical name35 MW expansion of #757
Queue ID800
Statusactive
Source statusActive
MarketOR
TechnologyOther
Capacity35.0 MW
StateOregon
CountyBaker
Point of interconnectionOBSY 230kV Switchyard
Requested (queue) date2026-03-25
Proposed in-service date2028-06-01
Operational date—
Withdrawn date—
Developer35 MW expansion of #757
Utility / transmission ownerIdaho Power Company

What changed

ObservedFieldOld valueNew valueMateriality
2026-11-23developer—35 MW expansion of #757low
2026-11-09phaseCS—low
2026-10-19phase—CSlow
2026-09-28phaseCS—low
2026-09-07phase—CSlow
2026-08-17phaseCSR—low
2026-08-03new_project—activehigh

Explore related data

Source last checked2026-11-23
Data last materially changed2026-11-23
Page data generated2026-11-26

Provenance: idahopower-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata