Oregon Interconnection Projects
interXdata tracks 2,343 interconnection projects in Oregon representing 292,627 MW of requested capacity. The dominant technology by capacity is Solar. The most active counties are Klamath, Umatilla, Morrow.
2,343Total projects
371Active
712Operational
1,189Withdrawn
292,627 MWRequested capacity
89,674 MWActive capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 880 | 80,288 MW |
| Battery | 191 | 54,938 MW |
| Wind | 369 | 52,591 MW |
| Solar+Battery | 195 | 40,539 MW |
| Gas | 197 | 30,969 MW |
| Other | 445 | 29,227 MW |
| Solar+Wind+Battery | 1 | 1,000 MW |
| Other Storage | 2 | 832 MW |
| Wind+Battery | 2 | 800 MW |
| Hydro | 44 | 708 MW |
| Coal | 3 | 518 MW |
| Geothermal | 14 | 217 MW |
Counties
| County | Projects | Requested capacity |
|---|---|---|
| Klamath | 244 | 26,252 MW |
| Umatilla | 194 | 23,663 MW |
| Morrow | 171 | 35,656 MW |
| Lake | 128 | 20,670 MW |
| Crook | 121 | 22,544 MW |
| Jefferson | 114 | 12,779 MW |
| Wasco | 103 | 22,993 MW |
| Sherman | 99 | 24,441 MW |
| Malheur | 89 | 2,918 MW |
| Gilliam | 86 | 14,107 MW |
| Linn | 79 | 7,062 MW |
| Jackson | 77 | 922 MW |
| Lane | 71 | 5,703 MW |
| Douglas | 70 | 4,596 MW |
| Deschutes | 70 | 9,291 MW |
| Multnomah | 69 | 6,536 MW |
| Clackamas | 66 | 1,978 MW |
| Marion | 63 | 4,600 MW |
| Baker | 61 | 2,634 MW |
| Harney | 49 | 9,076 MW |
| Columbia | 45 | 7,405 MW |
| Washington | 38 | 9,064 MW |
| Polk | 32 | 278 MW |
| Yamhill | 28 | 655 MW |
| Wallowa | 23 | 913 MW |
| Benton | 18 | 225 MW |
| Clatsop | 16 | 1,507 MW |
| Hood River | 15 | 508 MW |
| Union | 15 | 1,869 MW |
| Coos | 15 | 1,939 MW |
| Josephine | 8 | 18 MW |
| Curry | 7 | 1,358 MW |
| Morrow / Umatilla | 6 | 200 MW |
| Tillamook | 6 | 15 MW |
| Linn Or Lane | 5 | 880 MW |
| Washington Or | 5 | 899 MW |
| Klickitat | 5 | 897 MW |
| Grant | 5 | 258 MW |
| Lincoln | 4 | 39 MW |
| Wheeler | 3 | 400 MW |
Largest projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| NW Hillsboro-North Plains Semiconductor Plants Project (Phase 2) | L0561 | Other | 1,800.0 MW | active | Washington, Oregon |
| OR Queue Project G0756 — Solar in Lake, Oregon | G0756 | Solar | 1,650.0 MW | withdrawn | Lake, Oregon |
| OR Queue Project G0757 — Solar in Columbia, Oregon | G0757 | Solar | 1,650.0 MW | withdrawn | Columbia, Oregon |
| OR Queue Project G0754 — Solar in Marion, Oregon | G0754 | Solar | 1,650.0 MW | withdrawn | Marion, Oregon |
| OR Queue Project G0759 — Solar in Sherman, Oregon | G0759 | Solar | 1,650.0 MW | withdrawn | Sherman, Oregon |
| Pacific West Coast Cable | L0221 | Other | 1,600.0 MW | withdrawn | Columbia, Oregon |
| OR Queue Project G0748 — Solar in Klamath, Oregon | G0748 | Solar | 1,403.0 MW | withdrawn | Klamath, Oregon |
| West Hillsboro Data Center Project (Phase 1) | L0560 | Other | 1,400.0 MW | active | Washington, Oregon |
| OR Queue Project G1053 — Battery in Crook, Oregon | G1053 | Battery | 1,300.0 MW | active | Crook, Oregon |
| OR Queue Project G1051 — Solar in Deschutes, Oregon | G1051 | Solar | 1,300.0 MW | active | Deschutes, Oregon |
| OR Queue Project G1054 — Battery in Lake, Oregon | G1054 | Battery | 1,300.0 MW | active | Lake, Oregon |
| OR Queue Project G1052 — Solar in Deschutes, Oregon | G1052 | Solar | 1,300.0 MW | active | Deschutes, Oregon |
| OR Queue Project G1055 — Battery in Wasco, Oregon | G1055 | Battery | 1,300.0 MW | active | Wasco, Oregon |
| PACW Queue Project C4-093 — Solar+Battery in Klamath, Oregon | C4-093 | Solar+Battery | 1,280.0 MW | withdrawn | Klamath, Oregon |
| PACW Queue Project T2-081 — Solar+Battery in Harney, Oregon | T2-081 | Solar+Battery | 1,280.0 MW | active | Harney, Oregon |
| PACW Queue Project C4-092 — Solar+Battery in Harney, Oregon | C4-092 | Solar+Battery | 1,280.0 MW | withdrawn | Harney, Oregon |
| PACW Queue Project T2-082 — Solar+Battery in Klamath, Oregon | T2-082 | Solar+Battery | 1,280.0 MW | active | Klamath, Oregon |
| McNary 230 kV Substation | L0585 | Other | 1,250.0 MW | active | Linn, Oregon |
| OR Queue Project G0678 — Solar in Morrow, Oregon | G0678 | Solar | 1,200.0 MW | active | Morrow, Oregon |
| OR Queue Project G0697 — Solar in Crook, Oregon | G0697 | Solar | 1,200.0 MW | withdrawn | Crook, Oregon |
| Peoples Energy Resources | G87 | Gas | 1,200.0 MW | withdrawn | Klamath, Oregon |
| Sunstone Solar | 68396_PGB45 | Battery | 1,200.0 MW | active | Morrow, Oregon |
| Sunstone Solar | 68396_PGR45 | Solar | 1,200.0 MW | active | Morrow, Oregon |
| OR Queue Project G0695 — Battery in Crook, Oregon | G0695 | Battery | 1,200.0 MW | active | Crook, Oregon |
| OR Queue Project G0696 — Solar in Crook, Oregon | G0696 | Solar | 1,200.0 MW | withdrawn | Crook, Oregon |
| OR Queue Project G0983 — Solar in Sherman, Oregon | G0983 | Solar | 1,200.0 MW | withdrawn | Sherman, Oregon |
| Industrial Load Phase 2 | L0396 | Other | 1,152.0 MW | withdrawn | Morrow, Oregon |
| OR Queue Project G0501 — Gas in Klamath, Oregon | G0501 | Gas | 1,100.0 MW | withdrawn | Klamath, Oregon |
| OR Queue Project G0648 — Battery in Klamath, Oregon | G0648 | Battery | 1,100.0 MW | withdrawn | Klamath, Oregon |
| 1100MW Troutdale | G8 | Gas | 1,100.0 MW | withdrawn | Multnomah, Oregon |
Top developers in Oregon
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| PacifiCorp | 31 | 3,094 MW |
| Umatilla Electric Cooperative | 25 | 6,429 MW |
| Portland General Electric | 13 | 5,343 MW |
| Avangrid Power, LLC | 10 | 1,907 MW |
| Exelon Wind, LLC | 9 | 65 MW |
| Central Electric Cooperative, Inc. | 9 | 677 MW |
| City of Forest Grove | 9 | 506 MW |
| Northern Wasco County People's Utility District | 7 | 849 MW |
| Central Lincoln People's Utility District | 7 | 138 MW |
| Blachly-Lane County Cooperative Electric Association | 7 | 147 MW |
| Midstate Electric Cooperative, Inc. | 6 | 390 MW |
| OR Solar 2, LLC | 6 | 58 MW |
| Clatskanie People's Utility District | 5 | 446 MW |
| Adapture Renewables, Inc. | 5 | 27 MW |
| Oregon Wind Farms, LLC | 5 | 120 MW |
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-10-02 | Wheatridge Optimization II | new_project | — | active |
| 2026-10-02 | Wheatridge Optimization II | new_project | — | active |
| 2026-10-02 | Wheatridge Optimization I | new_project | — | active |
| 2026-10-02 | Wheatridge Optimization I | new_project | — | active |
| 2026-10-02 | Buckaroo Solar 1 | new_project | — | active |
| 2026-10-02 | Tutuilla Solar | new_project | — | active |
| 2026-10-02 | Lincoln Solar LLC (OR) | new_project | — | operational |
| 2026-10-02 | Univ of Oregon Central Power Station | operational_date | — | 2026-08-01 |
| 2026-10-02 | Univ of Oregon Central Power Station | proposed_online_date | 2026-08-01 | — |
| 2026-10-02 | Univ of Oregon Central Power Station | status | active | operational |
| 2026-09-28 | OR Queue Project AFS04 — Solar+Battery in Morrow, Oregon | new_project | — | active |
| 2026-09-28 | OR Queue Project AFS05 — Solar+Battery in Morrow, Oregon | new_project | — | active |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-10-11
Page data generated2026-10-11
Provenance: bpa-oasis; U.S. EIA — Form EIA-860M generator inventory (operating + planned); idahopower-oasis; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; pacificorp-oasis; pge-or-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.