7MEREDOSIA - 7TURNER 345.0kV (J4000)
7MEREDOSIA - 7TURNER 345.0kV is a 343.0 MW solar interconnection project in Scott, Illinois with a current status of operational. It is proposed to connect at 7MEREDOSIA - 7TURNER 345.0kV.
343.0 MWCapacity
OperationalStatus
—Market
SolarTechnology
Project facts
| Canonical name | 7MEREDOSIA - 7TURNER 345.0kV |
|---|---|
| Queue ID | J4000 |
| Status | operational |
| Source status | Active |
| Market | — |
| Technology | Solar |
| Capacity | 343.0 MW |
| State | Illinois |
| County | Scott |
| Point of interconnection | 7MEREDOSIA - 7TURNER 345.0kV |
| Requested (queue) date | 2025-04-29 |
| Proposed in-service date | 2030-01-28 |
| Operational date | 2030-01-28 |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | AMEREN ILLINOIS |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-29 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata