Illinois Interconnection Projects
interXdata tracks 2,701 interconnection projects in Illinois representing 281,208 MW of requested capacity. The dominant technology by capacity is Solar. The most active counties are Cook, Lee, Will.
2,701Total projects
290Active
1,440Operational
938Withdrawn
281,208 MWRequested capacity
27,399 MWActive capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 1,151 | 82,601 MW |
| Wind | 493 | 78,428 MW |
| Gas | 420 | 42,331 MW |
| Other | 317 | 32,951 MW |
| Battery | 282 | 32,422 MW |
| Coal | 20 | 6,095 MW |
| Nuclear | 5 | 4,090 MW |
| Solar+Battery | 9 | 1,180 MW |
| Wind+Other | 1 | 400 MW |
| Solar+Other | 1 | 360 MW |
| Solar+Wind | 1 | 199 MW |
| Wind+Battery | 1 | 150 MW |
Counties
| County | Projects | Requested capacity |
|---|---|---|
| Cook | 154 | 5,815 MW |
| Lee | 145 | 15,442 MW |
| Will | 141 | 15,853 MW |
| Kankakee | 79 | 5,477 MW |
| DeKalb | 69 | 3,426 MW |
| Ogle | 68 | 8,086 MW |
| Livingston | 68 | 9,845 MW |
| Grundy | 65 | 12,598 MW |
| Stephenson | 62 | 3,583 MW |
| McLean | 61 | 8,218 MW |
| McHenry | 60 | 3,043 MW |
| Bureau | 58 | 3,840 MW |
| Kane | 55 | 825 MW |
| Winnebago | 55 | 5,187 MW |
| Champaign | 52 | 2,272 MW |
| Lasalle | 44 | 3,878 MW |
| Whiteside | 42 | 2,107 MW |
| Christian | 40 | 8,060 MW |
| LaSalle | 38 | 3,508 MW |
| Henry | 37 | 3,591 MW |
| Tazewell | 37 | 5,737 MW |
| Vermilion | 34 | 4,625 MW |
| Lake | 34 | 2,818 MW |
| Sangamon | 33 | 6,182 MW |
| Logan | 32 | 3,395 MW |
| Macon | 32 | 3,193 MW |
| Kendall | 32 | 5,431 MW |
| St Clair | 30 | 1,976 MW |
| Perry | 29 | 3,403 MW |
| Ford | 29 | 3,702 MW |
| Clay | 27 | 2,328 MW |
| Clinton | 27 | 382 MW |
| DuPage | 26 | 1,119 MW |
| Rock Island | 26 | 6,058 MW |
| Adams | 26 | 1,745 MW |
| Madison | 26 | 1,313 MW |
| Peoria | 26 | 2,550 MW |
| Shelby | 25 | 4,400 MW |
| Woodford | 25 | 2,885 MW |
| Williamson | 24 | 2,771 MW |
Largest projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Dresden Tazewell Mole Creek | AE1-222 | Gas | 2,562.7 MW | withdrawn | Grundy, Illinois |
| MISO Queue Project J371 — Nuclear in Ogle, Illinois | J371 | Nuclear | 2,325.0 MW | withdrawn | Ogle, Illinois |
| Plano 345 kV | AF1-200 - moved to TC1 | Other | 2,100.0 MW | withdrawn | Kendall, Illinois |
| MISO Queue Project IP14 — Coal in Washington, Illinois | IP14 | Coal | 1,500.0 MW | operational | Washington, Illinois |
| MISO Queue Project G902 — Wind in Winnebago, Illinois | G902 | Wind | 1,500.0 MW | withdrawn | Winnebago, Illinois |
| MISO Queue Project IP05 — Other in Randolph, Illinois | IP05 | Other | 1,500.0 MW | withdrawn | Randolph, Illinois |
| MISO Queue Project J372 — Nuclear in Rock Island, Illinois | J372 | Nuclear | 1,373.0 MW | withdrawn | Rock Island, Illinois |
| Kendall-Tazewell-Dresden-Mole Creek | AC1-153 | Gas | 1,300.0 MW | withdrawn | Grundy, Illinois |
| Davis Creek-Burnham | AC1-067 | Gas | 1,254.0 MW | withdrawn | Cook, Illinois |
| Byron Generating Station | 6023_2 | Other | 1,224.9 MW | operational | Ogle, Illinois |
| Byron Generating Station | 6023_1 | Other | 1,224.9 MW | operational | Ogle, Illinois |
| Braidwood Generation Station | 6022_1 | Other | 1,224.9 MW | operational | Will, Illinois |
| Braidwood Generation Station | 6022_2 | Other | 1,224.9 MW | operational | Will, Illinois |
| Sullivan 765 kV | Y2-095 | Other | 1,211.0 MW | withdrawn | Randolph, Illinois |
| Elwood | AC1-204 | Gas | 1,200.9 MW | operational | Will, Illinois |
| Steward Creek Solar Phase 1 | 65301_SC1 | Solar | 1,200.0 MW | active | Lee, Illinois |
| LaSalle Generating Station | 6026_2 | Other | 1,170.0 MW | operational | LaSalle, Illinois |
| LaSalle Generating Station | 6026_1 | Other | 1,170.0 MW | operational | LaSalle, Illinois |
| Kendall-Tazewell & Dresden-Mole Creek | AB1-122 | Gas | 1,160.0 MW | operational | Grundy, Illinois |
| Clinton Power Station | 204_1 | Other | 1,138.3 MW | operational | DeWitt, Illinois |
| Austin Substation 345kV Bus | J955 | Gas | 1,040.0 MW | operational | Sangamon County, Illinois |
| Collins | AA2-035 | Gas | 1,019.3 MW | withdrawn | Grundy, Illinois |
| Dresden Generating Station | 869_2 | Other | 1,009.3 MW | operational | Grundy, Illinois |
| Dresden Generating Station | 869_3 | Other | 1,009.3 MW | operational | Grundy, Illinois |
| Quad Cities Generating Station | 880_2 | Other | 1,009.3 MW | operational | Rock Island, Illinois |
| Quad Cities Generating Station | 880_1 | Other | 1,009.3 MW | operational | Rock Island, Illinois |
| Quad Cities Wind | V4-074 | Wind | 1,000.0 MW | withdrawn | Hancock, Illinois |
| Powerton | 879_5 | Other | 892.8 MW | operational | Tazewell, Illinois |
| Powerton | 879_6 | Other | 892.8 MW | operational | Tazewell, Illinois |
| Prairie State Generating Station | 55856_PC2 | Other | 883.0 MW | operational | St Clair, Illinois |
Top developers in Illinois
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Deriva Energy | 8 | 1,320 MW |
| Steward Creek Solar, LLC | 8 | 1,240 MW |
| Invenergy | 7 | 798 MW |
| Wapella Bluffs Wind Project, LLC | 5 | 950 MW |
| Leeward Renewable Energy Development, LLC | 5 | 1,213 MW |
| Blue Violet Energy, LLC | 3 | 259 MW |
| Mound Solar, LLC | 3 | 600 MW |
| Golden West Energy | 3 | 415 MW |
| Plano Skies Energy Center, LLC | 3 | 292 MW |
| Bison Meadows Wind Project, LLC | 3 | 299 MW |
| Constellation Energy Generation, LLC | 3 | 392 MW |
| Aurora Solar LLC | 3 | 350 MW |
| Minonk Solar, LLC | 2 | 250 MW |
| Red Maple Solar, LLC | 2 | 195 MW |
| Rolling Farms Wind Project, LLC | 2 | 106 MW |
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-11-11 | Mazon-Crescent Ridge 138 kV | status | active | operational |
| 2026-11-11 | Mazon-Crescent Ridge 138 kV | operational_date | — | 2026-11-30 |
| 2026-11-11 | Mazon-Crescent Ridge 138 kV | proposed_online_date | 2026-11-30 | — |
| 2026-11-05 | 7COFFEEN - 7PANA 345.0kV | withdrawn_date | — | 2026-10-20 |
| 2026-11-05 | 7COFFEEN - 7PANA 345.0kV | status | operational | withdrawn |
| 2026-11-05 | SUB 39 - CORDOVA 345.0kV | withdrawn_date | — | 2026-10-20 |
| 2026-11-05 | SUB 39 - CORDOVA 345.0kV | status | operational | withdrawn |
| 2026-11-05 | Turkey Hill 138 kV | withdrawn_date | — | 2026-10-20 |
| 2026-11-05 | Turkey Hill 138 kV | status | operational | withdrawn |
| 2026-11-05 | 4WLTNVL TP 138 kV | withdrawn_date | — | 2026-10-20 |
| 2026-11-05 | 4WLTNVL TP 138 kV | status | operational | withdrawn |
| 2026-11-05 | Gilman - Watseka 138kV | withdrawn_date | — | 2026-10-20 |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-11-26
Page data generated2026-11-26
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; MISO — generator interconnection queue; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.