AC Landfill Energy Units 1, 2, 3 (S07)

AC Landfill Energy Units 1, 2, 3 is a 100.0 MW other interconnection project with a current status of withdrawn. It is proposed to connect at Keystone-Branchburg.

100.0 MWCapacity
WithdrawnStatus
PJMMarket
OtherTechnology

Project facts

Canonical nameAC Landfill Energy Units 1, 2, 3
Queue IDS07
Statuswithdrawn
Source statuswithdrawn
MarketPJM
TechnologyOther
Capacity100.0 MW
State
County
Point of interconnectionKeystone-Branchburg
Requested (queue) date2007-03-01
Proposed in-service date
Operational date
Withdrawn date2013-02-20
Developer
Utility / transmission ownerAPS

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata