AL Queue Project TC25-059 — Solar in Madison, Alabama

AL Queue Project TC25-059 — Solar in Madison, Alabama is a 110.0 MW solar interconnection project in Madison, Alabama with a current status of active. It is proposed to connect at Limestone 161kV Substation.

110.0 MWCapacity
ActiveStatus
ALMarket
SolarTechnology

Project facts

Canonical nameAL Queue Project TC25-059 — Solar in Madison, Alabama
Queue IDTC25-059
Statusactive
Source statusFacilities Study
MarketAL
TechnologySolar
Capacity110.0 MW
StateAlabama
CountyMadison
Point of interconnectionLimestone 161kV Substation
Requested (queue) date2024-10-01
Proposed in-service date2027-04-01
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerTennessee Valley Authority

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-21phaseCluster StudyFacilities Studylow
2026-08-24poi_nameLimestone 161kV BusLimestone 161kV Substationlow
2026-08-03new_project—activehigh

Explore related data

Source last checked2026-11-23
Data last materially changed2026-11-23
Page data generated2026-11-26

Provenance: tva-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.