Alcoa Substation (L0325)

Alcoa Substation is a 6.0 MW other interconnection project in Clark, Washington with a current status of withdrawn. It is proposed to connect at BPA Alcoa Substation.

6.0 MWCapacity
WithdrawnStatus
WAMarket
OtherTechnology

Project facts

Canonical nameAlcoa Substation
Queue IDL0325
Statuswithdrawn
Source statusWITHDRAWN
MarketWA
TechnologyOther
Capacity6.0 MW
StateWashington
CountyClark
Point of interconnectionBPA Alcoa Substation
Requested (queue) date2011-02-15
Proposed in-service date2013-09-01
Operational date
Withdrawn date
DeveloperClark Public Utilities
Utility / transmission ownerBonneville Power Administration

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata