Clark Public Utilities — Interconnection Portfolio
Clark Public Utilities is associated with 14 tracked interconnection projects representing 1,647 MW of requested capacity.
Entity resolution: this developer rolls up 2 source organization name(s) that were auto-matched into a single canonical cluster. Attribution is inferred from source records and may include related special-purpose entities.
14Projects
2Active
3Operational
9Withdrawn
1,647 MWRequested capacity
0Markets
Capacity by technology
| Technology | Projects | Requested capacity |
|---|---|---|
| Other | 9 | 1,010 MW |
| Gas | 4 | 636 MW |
| Solar | 1 | 1 MW |
Geographic footprint
| State | Projects |
|---|---|
| Washington | 12 |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| New Rail Loop Load | L0470 | Other | 300.0 MW | withdrawn | Clark, Washington |
| Clark Public Utilities | G46-01 | Gas | 250.0 MW | withdrawn | Clark, Washington |
| River Road Generating Plant | G129 | Gas | 240.0 MW | operational | Clark, Washington |
| Project Bald Eagle | L0472 | Other | 230.0 MW | withdrawn | Clark, Washington |
| Project Quantum | L0411 | Other | 160.0 MW | withdrawn | Clark, Washington |
| Carborundum Substation Upgrade | L0460 | Other | 120.0 MW | withdrawn | Clark, Washington |
| Project Osprey | L0548 | Other | 100.0 MW | withdrawn | Clark, Washington |
| WA Queue Project G28 — Gas in Clark, Washington | G28 | Gas | 100.0 MW | withdrawn | Clark, Washington |
| River Road Generating Plant | G1008 | Gas | 46.0 MW | operational | Clark, Washington |
| VIC Load Addition | L0634 | Other | 40.0 MW | active | Clark, — |
| Project Echo | L0654 | Other | 29.0 MW | active | Clark, — |
| New Camas Substation | L0487 | Other | 25.0 MW | withdrawn | Clark, Washington |
| Alcoa Substation | L0325 | Other | 6.0 MW | withdrawn | Clark, Washington |
| Community Solar East | G0968 | Solar | 1.0 MW | operational | Clark, Washington |
Recent material changes
No material field-level changes have been recorded against these projects since the baseline snapshot. interXdata records changes as new source snapshots are ingested and diffed.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Monitor Clark Public Utilities's portfolio across all markets.
Start tracking with interXdata