Amphion Solar Phase 3 (28INR0344)

Amphion Solar Phase 3 is a 115.4 MW solar interconnection project in Atascosa, Texas with a current status of operational. It is proposed to connect at TAP 345KV (#5709) Fowlerton - (#5901) SAN MIGUEL LINE Ckt-2.

115.4 MWCapacity
OperationalStatus
AtascosaMarket
SolarTechnology

Project facts

Canonical nameAmphion Solar Phase 3
Queue ID28INR0344
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketAtascosa
TechnologySolar
Capacity115.4 MW
StateTexas
CountyAtascosa
Point of interconnectionTAP 345KV (#5709) Fowlerton - (#5901) SAN MIGUEL LINE Ckt-2
Requested (queue) date2025-04-21
Proposed in-service date
Operational date2029-11-15
Withdrawn date
DeveloperAmphion Solar, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata