Andrews County 230kV (GEN-2016-062)

Andrews County 230kV is a 250.7 MW wind interconnection project in Andrews, Texas with a current status of withdrawn. It is proposed to connect at Andrews County 230kV.

250.7 MWCapacity
WithdrawnStatus
TXMarket
WindTechnology

Project facts

Canonical nameAndrews County 230kV
Queue IDGEN-2016-062
Statuswithdrawn
Source statusWITHDRAWN
MarketTX
TechnologyWind
Capacity250.7 MW
StateTexas
CountyAndrews
Point of interconnectionAndrews County 230kV
Requested (queue) date2016-03-29
Proposed in-service date
Operational date
Withdrawn date2019-08-27
Developer
Utility / transmission ownerSPS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata